Milan Malpensa (MXP): the CASCADE pilot site, 2014–2015
Milan Malpensa as a CASCADE pilot: the airport's energy system as the project described it, the Satellite A installation and the savings reported in 2015.
Milano Malpensa was one of the two airports where the CASCADE research project tested its fault detection and energy management tools. Its operator, SEA (Società per Azioni Esercizi Aeroportuali), was a member of the project consortium. Installations at Malpensa were completed and commissioned in May 2014, a few months after the first pilot at Rome Fiumicino, and ran until the project ended in March 2015.
This page summarises what the project recorded about the airport and what it reported from the pilot. Figures describing the airport date from around 2010 to 2012 and are given as the project stated them; they should not be read as a description of Malpensa today.
The airport as the project described it
The project's site page introduced Malpensa as Italy's second-largest airport, with 18.7 million passengers in 2010. It gave the airport's electricity consumption as roughly 140 GWh a year.
The most distinctive feature of Malpensa's energy system, as the project described it, was a large trigeneration plant: about 80 MW of electrical capacity, about 90 MW of heating capacity and about 36 MW of chilled water production through absorption chillers. Large air handling units served Terminal 1.
The page also noted that the airport held ACI EUROPE's Airport Carbon Accreditation at the "neutrality" level at the time, and listed energy measures already in place. These included shutting down a runway at night, efficient motors, monitoring of HVAC set-points, additional metering and low-energy lighting.
What trigeneration means for energy analysis
This section is Cascade's own explanation.
A trigeneration plant generates electricity, typically with gas engines or turbines, recovers the waste heat for space heating, and uses part of that heat to drive absorption chillers that produce chilled water. Done well, it extracts much more useful energy from each unit of fuel than separate production would.
It also complicates the job of finding and valuing waste in the buildings it serves. A kilowatt-hour of chilled water saved at an air handling unit is not worth the same as a kilowatt-hour of electricity, and its value depends on how the chilled water was produced at that moment: by an absorption chiller using recovered heat, or by an electric chiller at peak. That is one reason the project reported its Malpensa results as three separate quantities rather than one total.
The CASCADE installation
The project's news reported that installations at Malpensa were completed and commissioned in May 2014. The work concentrated on the air handling units supplying Satellite A. As at Fiumicino, the approach combined data from the existing building management system with additional sensors and meters, fed into the project's fault detection and diagnosis tools.
According to the project's final newsletter, published in July 2015, the savings potential identified for the AHUs supplying Satellite A was:
| Energy stream | Savings potential reported (per year) |
|---|---|
| Electricity | 126 MWh |
| Heat | 309 MWh |
| Chilled water | 262 MWh |
The newsletter also reported that both pilot airports showed savings potentials of "up to 20%" on the systems studied, with a payback of less than two years for the solution. As with all pilot results, these are estimates of what correcting the identified faults would save, not long-term measured savings; see our pilot airports overview for a note on reading such figures.
Malpensa in the research papers
Malpensa appears in two of the scientific publications associated with the project.
The first is a paper presented at Building Simulation 2013, the conference of the International Building Performance Simulation Association held in Chambéry, France, in August 2013. Written by Luis M. Blanes Restoy, Andrea Costa and Marcus M. Keane, it used Malpensa as a case study for how building simulation could support an ISO 50001 energy management system and fault detection and diagnosis. Simulation is useful in this role because it provides a model of how a system should behave, against which measured behaviour can be compared.
The second is a 2015 journal paper in Advanced Engineering Informatics on an ontology-based facility data model for energy management, written by authors from partner organisations, which used both Malpensa and Fiumicino as test beds. Full citations for both are in our guide to CASCADE publications.
The March 2015 workshop
Near the end of the project, on 13 March 2015, a workshop was held at Malpensa jointly with S4ECoB, another FP7 research project on energy efficiency in buildings. The project's news headline for the event carried the date 19 March, but the body of the item, the invitation page and the filename of the draft agenda all give 13 March, which we take to be correct. The event is also listed in our project timeline.
Malpensa today
The passenger numbers, plant capacities and accreditation level above are historical. Traffic at Malpensa, its energy systems and its carbon management have all changed in the years since the project, and current figures should be taken from the operator's own publications. The Airport Carbon Accreditation programme has also added higher levels since the project's time, so the "neutrality" level recorded by the project should not be compared directly with today's status; the programme publishes the current accreditation of each participating airport.
Further reading on Cascade
For present-day context, see our articles on heating, ventilation and air-conditioning in airport terminals, Airport Carbon Accreditation and district heating and cooling networks. The companion pilot page covers Rome Fiumicino, and all archive pages are listed on the CASCADE project archive index.
References
- CASCADE project record (CORDIS). European Commission, CORDIS
- Archived Malpensa pilot page (captured March 2016). Arquivo.pt
- CASCADE Newsletter No. 6, July 2015 (archived copy). Arquivo.pt
- Simulation to support ISO 50001 energy management systems and fault detection and diagnosis: case study of Malpensa Airport (Building Simulation 2013). IBPSA
- Archived workshop page, Malpensa, 13 March 2015. Arquivo.pt