CASCADE pilot airports: Milan Malpensa and Rome Fiumicino

The two Italian airports where CASCADE installed and validated its fault detection tools between 2013 and 2015, and the savings potential it reported.

Published
Reading time
4 min
Byline
Cascade

A research method for airports has to be tested in airports. CASCADE did this at two of Italy's largest: Milano Malpensa, run by SEA, and Roma Fiumicino, run by Aeroporti di Roma. Both operators were members of the project consortium, which gave the researchers access to real plant, real building management systems and the staff who operate them.

This page gives an overview of the two pilots: what was installed, when, and what the project reported at the end. Each airport has its own page with more detail. All figures below are historical and are attributed to the project's own publications.

The pilots at a glance

Rome Fiumicino (FCO)Milan Malpensa (MXP)
Operator (consortium partner)Aeroporti di Roma S.p.A.SEA S.p.A.
Area studiedTerminal 1Air handling units supplying Satellite A
Installation completedDecember 2013May 2014
Validation periodto March 2015to March 2015
Reported savings potential, electricity363 MWh/yr126 MWh/yr
Reported savings potential, heat691 MWh/yr309 MWh/yr
Reported savings potential, chilled water527 MWh/yr262 MWh/yr
Detailed pageFiumicino pilotMalpensa pilot

Savings figures are those given in the project's sixth and final newsletter (July 2015). For Fiumicino the newsletter also estimated the value at about EUR 90,000 a year and the emissions reduction at about 230 tonnes of CO₂ a year.

Why these two airports

Malpensa and Fiumicino are the two main intercontinental gateways in Italy, and both had large, complex energy systems at the time of the project: Malpensa with a trigeneration plant producing electricity, heat and chilled water, Fiumicino with a cogeneration unit as part of a larger thermal plant. Both operators were also active in energy and carbon management in their own right. The project's site pages recorded that each held Airport Carbon Accreditation at the time, Malpensa at the "neutrality" level and Fiumicino at the "optimisation" level.

Testing at two different operators also mattered for the project's claim to be technology-neutral. A method that only worked with one airport's building management system would have been of limited use elsewhere.

What was installed, and when

According to the project's news items, the work at the sites followed a sequence that is typical of building-services retrofit projects:

  1. Design and preparation (2012–2013). The project reported that its demonstration phase began in December 2012. The groundwork is reflected in its first public deliverables, whose titles cover the energy characterisation of European airports and a methodology for energy-efficient airports.
  2. Procurement. A tender for sensors, meters and data loggers was won by an installation firm based in Padua, with a kick-off meeting at Fiumicino in August 2013.
  3. Installation and commissioning. The Fiumicino installation was completed and commissioned in December 2013. Malpensa followed in May 2014.
  4. Operation and validation. From then until the end of the project in March 2015, the tools ran on live data, and the project's archived pilot overview describes the systems as installed and validated over this period.

The project's site pages identified large chiller plants, cooling towers and air handling units as the main targets, consistent with the project-wide focus on HVAC.

Results as reported

The final newsletter summarised the outcome as savings potentials of "up to 20%" at both pilots, with a payback period of less than two years for the CASCADE solution. Both figures compare favourably with the targets the project set at the outset, which were a 20% reduction and a three-year return on investment.

One caution applies. In July 2014, while the pilots were still running, a CORDIS news article gave an earlier estimate of roughly 500 MWh, 3,500 tonnes of CO₂ and EUR 70,000 a year. Those three numbers cannot all describe the same savings: 500 MWh of energy could not produce anything like 3,500 tonnes of CO₂ at any realistic emission factor. We therefore rely on the later, more detailed figures from the final newsletter and attribute them to the project.

Notable events at the pilots included a significant fault in an air handling unit's cooling coil found at Fiumicino in June 2014, and a joint workshop with another FP7 project, S4ECoB, held at Malpensa on 13 March 2015. Both are covered on the individual airport pages and in our project timeline.

How to read pilot savings figures

This section is Cascade's own commentary rather than part of the historical record.

A "savings potential" is the reduction the project estimated would follow if the faults it found were corrected and the improvements it identified were implemented. It is not the same as savings measured over several years after the project ended. Establishing the latter requires a baseline, an agreed method for adjusting for weather and traffic, and continued metering, which is the subject of measurement and verification (M&V) practice. We have found no public record of long-term verified savings at either airport attributable to CASCADE.

That is not a criticism peculiar to this project; most research pilots end before long-term verification is possible. It is, however, the right way to read any figure of this kind.

Further reading on Cascade

For present-day context, see our articles on energy efficiency in airports, Airport Carbon Accreditation and measurement and verification of energy savings. All archive pages are listed on the CASCADE project archive index.

References

  1. CASCADE project record (CORDIS). European Commission, CORDIS
  2. Archived 'Project airports' page (captured March 2016). Arquivo.pt
  3. Archived CASCADE news page (captured March 2016). Arquivo.pt
  4. CASCADE Newsletter No. 6, July 2015 (archived copy). Arquivo.pt
  5. CASCADE – reducing energy use by airports. European Commission, CORDIS